Production

Correct wrong materials and push the change to production

Fix excess or wrong material types in the design and re-sync the work order so production picks it up.

  1. Correct wrong or excess material types by selecting the units and using the change-material action.

    ✓ 19 అక్టోబర్, 2026న ప్రోడక్ట్‌లో తనిఖీ చేయబడింది
  2. Material changes such as switching a panel core from BWP to HDHMR are made in the design (QC mode's Materials Used / Units / Panels views), not in the production output screen.

    ✓ 19 అక్టోబర్, 2026న ప్రోడక్ట్‌లో తనిఖీ చేయబడింది
  3. The production output picks the change up once the work order is re-synced with the design and published.