Infurnia Help
Production

How the not-started panel count is calculated

Learn which panels the not-started count includes in production tracking and when it changes.

  1. In production tracking, the "not started" count shows panels on which no process has begun.

  2. If any station has processed a panel, it no longer counts as not started even if an earlier station was not scanned.

  3. For example, if edge banding is complete for all panels, the not-started count reads zero even though cutting may show missing panels.

  4. The count increases only for panels where nothing has happened at any station.